LogoConduit
Conduit Electrical — K-12 & University Infrastructure
2,400+
ClassroomsRewired Across K-12 & University Campuses
98.7%
First-PassInspection Rate — Every AHJ, Every Building Type
$14M
Bond-FundedProjects Delivered On Schedule, Zero Claims

Every wire labeled. Every conduit run straight. Every panel schedule matching reality. That's not a promise — it's what our inspection record proves.

Project Record

Every building type.
Every scope of work.

Four institutions. Four different challenges. The same result: code-compliant, on schedule, no surprises.


K-8 CampusRancho Cielo Middle School·San Bernardino Unified, CA·2023

Condemned Science Wing, Aluminum Wiring Throughout — 9 Weeks to Full Occupancy

Middle school hallway with exposed conduit runs during electrical renovation
34
Classrooms Re-wired
312
Arc-Fault Breakers
400A → 1,200A
Service Upgrade
61
Days to Inspection

The Challenge

The 1962 building had aluminum branch circuit wiring in every classroom, a 400A service that hadn't been touched since 1978, and a fire alarm panel the district's own inspector had flagged as non-compliant with NFPA 72 Chapter 10. The science wing was tagged out of service.

Scope of Work

Full service upgrade to 1,200A, copper re-wire of 34 classrooms, 312 arc-fault breakers, new fire alarm loop with addressable devices, EV conduit stub-outs in faculty lot.

Project Timeline

Discovery Walkthrough

Infrared scan of all panels, aluminum wiring audit, fire alarm loop trace — completed in 2 days before bid.

Scope & Phasing Plan

Phased re-wire sequenced around spring testing calendar. Science wing prioritized for bond compliance deadline.

Summer Construction

9-week window. 22 electricians on site. Parallel crews — service upgrade crew and classroom re-wire crew — no single-point bottlenecks.

Energized & Inspected

AHJ sign-off on Day 61. Fire marshal clearance Day 63. Science wing re-opened Day 1 of fall semester.

They handed me a panel schedule on Day 1 that matched what was actually in the walls. I've never had a contractor do that before the work started.

MW
Marcus WebbDirector of Facilities, San Bernardino Unified
K-5 CampusSage Canyon Elementary·Desert Sands USD, CA·2022

Portable Classrooms on Aging Feeders — Rewired 18 Portables Without a Single Lost School Day

Elementary school campus exterior with portable classroom buildings
18
Portables Upgraded
0
School Days Lost
60A → 100A ea.
Feeder Capacity
18 Rooms
Title 24 Controls

The Challenge

18 portable classrooms fed by undersized 60A feeders from a 1984 distribution panel. HVAC upgrades had pushed loads past 85% capacity. Two portables had tripped their main breakers 11 times in one semester.

Scope of Work

New 400A sub-panel for portable yard, individual 100A feeders to each portable, Title 24 lighting controls in all 18 units, tamper-resistant receptacles throughout.

Project Timeline

Load Analysis

Metered actual loads across all 18 portables during peak HVAC periods. Documented 94% average load factor — 34% over safe design threshold.

Phased Weekend Work

Trenching and conduit installation on 3 consecutive weekends. Zero impact on school schedule.

Panel Cutover

Friday afternoon cutover, restored by Sunday evening. Principal confirmed Monday morning power-on.

Title 24 Sign-Off

Lighting control commissioning and CEC compliance documentation delivered same day as final inspection.

We had parents calling about the tripped breakers. After Conduit finished, we haven't had a single complaint. The principal stopped worrying about Monday mornings.

PN
Patricia NguyenChief Business Official, Desert Sands USD
Community CollegeMojave Community College·Mojave CCD, CA·2024

Science & Technology Building Modernization — $4.2M Bond Scope, Delivered 11 Days Early

Community college science building exterior during modernization construction
$4.2M
Bond Scope
48
EV Charging Stalls
11
Days Ahead of Schedule
2 (Owner-Directed)
Change Orders

The Challenge

The 1971 S&T building needed full electrical modernization as part of a Measure B bond program. The college's bond oversight committee required monthly progress reporting, independent inspector access, and a hard completion date tied to fall enrollment targets.

Scope of Work

2,400A switchgear replacement, lab-grade isolated ground circuits in 8 chemistry and physics labs, 400A EV charging infrastructure for 48 faculty/staff spaces, new emergency generator with automatic transfer switch, full fire alarm addressable system per NFPA 72.

Project Timeline

Bond Coordination

Submitted DSA-compliant submittals in Week 1. Established weekly progress meeting rhythm with bond oversight team.

Switchgear Shutdown

Coordinated 72-hour campus power outage during spring break. Temporary power for critical systems maintained throughout.

Lab Circuit Installation

Isolated ground circuits for analytical equipment. Every circuit meggered and documented before equipment hook-up.

Substantial Completion

Certificate of Occupancy issued July 12 — 11 days ahead of August 1 bond milestone. $0 in liquidated damages.

The bond committee asked me to name one contractor I'd put in front of voters again. I named Conduit without hesitation. They treated our public dollars like their own.

DJO
Dr. James OkaforVice President, Administrative Services, Mojave CCD
Research UniversityArroya State University·CSU System, CA·2025

Campus Microgrid Installation — 2.4MW Solar + Storage, 14-Building Integration

University campus rooftop with solar panel installation and electrical infrastructure
2.4MW
Solar Capacity
1.8MWh
Battery Storage
14
Buildings Integrated
$1.4M
Net University Savings

The Challenge

The university's sustainability office had a 2025 carbon-neutral target and a Prop 39 grant covering 60% of a microgrid installation. The challenge: integrating 14 existing buildings with wildly inconsistent electrical infrastructure — some vintage 1950s, some brand new — into a single coordinated system without disrupting active research labs running 24/7 experiments.

Scope of Work

2.4MW rooftop solar across 6 buildings, 1.8MWh battery storage, microgrid controller with demand response, 14-building SCADA integration, research lab uninterruptible power provisions, full utility interconnection agreement.

Project Timeline

Infrastructure Audit

Electrical audit of all 14 buildings. Discovered 3 buildings with incompatible metering — redesigned integration before breaking ground.

Research Lab Coordination

Scheduled all switching events around lab experiment calendars. Zero experiments interrupted across 18 months of construction.

Microgrid Commissioning

72-hour island mode test with simulated utility outage. System maintained full campus power within 800ms of grid disconnect.

Prop 39 Closeout

Grant documentation package submitted 3 weeks early. Full reimbursement received. University saved $1.4M net of Conduit fees.

We've worked with firms twice the size of Conduit on projects half as complex. None of them coordinated research lab schedules the way these people did. They understood what was at stake.

DSL
Dr. Sarah LindqvistDirector of Capital Projects, Arroya State University
What We Do

Every scope a school facility needs.
None it doesn't.

Panel Upgrades & Service Entrance

From 200A residential-era panels to 4,000A switchgear. We size, spec, and install — then hand you a panel schedule that matches.

Load AnalysisDSA CompliantArc-Flash Labeling

Fire Alarm Systems

Addressable FACP installations, loop inspections, annual testing, and full NFPA 72 documentation packages for AHJ submittals.

NFPA 72Addressable SystemsAnnual Testing

Lighting & Title 24

LED retrofits, occupancy controls, and daylighting sensors — engineered and commissioned to pass CEC Title 24 on the first visit.

Title 24LED RetrofitOccupancy Controls

EV Charging Infrastructure

Level 2 and DC fast chargers for faculty lots, student parking, and fleet yards. Utility coordination and SGIP incentive documentation included.

SGIP IncentivesLevel 2 & DCFCUtility Coordination

New Construction & Modernization

Bond-measure scopes from schematic design through DSA closeout. We know the paperwork as well as the wire.

Bond MeasureDSA CloseoutMeasure B/C/E

Emergency & Maintenance

24/7 emergency response for campus power failures. Scheduled maintenance programs that prevent the 2 AM call.

24/7 ResponsePreventive MaintenanceGenerator Service
Credentials & Compliance

Your inspector's checklist
is our job description.

C-10 Licensed
California Electrical Contractor
NFPA 72 Certified
Fire Alarm Installation & Testing
Title 24 Compliant
CEC Lighting & Energy Code
DSA Registered
Division of the State Architect
OSHA 30 Trained
All Foremen & Superintendents
IBEW Local 440
Journeyman Electricians

NFPA 72

Fire Alarm & Signaling Code

Addressable device spacing, pathway survivability, and AHJ documentation packages — we know what Chapter 10 inspectors look for.

Title 24 Part 6

California Energy Code

Occupancy sensing, daylighting controls, and demand-responsive lighting — commissioned and documented for CEC compliance on first inspection.

NEC 2023

National Electrical Code

Arc-fault protection, GFCI requirements, and service entrance compliance — we track code adoption by jurisdiction, not just state.

DSA IR A-8

Inspector of Record Requirements

Bond-measure projects require DSA-registered contractors. We maintain current registration and have closed out 23 DSA projects without a single unresolved correction.

Get Started

Request a Facility
Walkthrough.

We'll come to your campus, review your panel schedules, and give you a written scope — not a ballpark. No obligation. Most walkthroughs take 90 minutes and produce a document your bond committee can actually use.

Same-week availability
We prioritize school schedules, not ours.
📋
Written scope, not a quote
A real document. Panel schedules, phasing, code references.
🔒
No sales pressure
Our walkthrough report is yours to use with any contractor.

No obligation. Walkthrough report is yours to keep.

K-12 Electrical Compliance Checklist

Title 24 · NFPA 72 · NEC 2023 · DSA Requirements

The exact items your next AHJ inspector will look for — organized by system type so you can walk your building before they do.

NFPA 72 addressable device spacing requirements
Title 24 occupancy sensor placement rules
Arc-fault protection scope by room type
DSA submittal checklist for bond projects
Service entrance labeling requirements
Emergency lighting test documentation
+ 24 more items in the full checklist
Free Download

Know what your
inspector sees
before they arrive.

30 items. Every Title 24 and NFPA 72 requirement your inspector will check on a K-12 campus. Built from our 98.7% first-pass rate — this is what we verify before we call for inspection.

No spam. One email with the PDF. That's it.